Bond Project Updates - Week of November 9, 2026

Here’s the latest on the ongoing construction projects taking place at KCKPS:
Argentine Middle School
Crews have worked on the following:
Area E
- Moving formwork for cast-in-place wall
- Masonry installations at elevator and fire wall
- Plumbing sleeving through masonry
Area D
- Plumbing undeground sleeving
- Foot prepartions
Area E
- Final footing pours
- Rebar and formwork for cast-in-place wall
- Structural masonry installations
- Undeground electrical and plumbing
Area D
- Footing excavations
- Tying rebar, pouring footings
Woodlands Hills Elementary
Crews have worked on the following:
Area A (Week of 11/9)
- Completed underslab MEP
- Began pouring slab
- Completed footings for bridge
Area C
- Began underslab MEP
- Contiuned structural concrete wall
- Completed site utilities surrounding pad
Area A (Week of 11/16)
- Complete slab pours
- Begin footings for precast gym
- Prepare for steel arrival
Area C (week of 11/16)
- Complete cast-in place wall
- Continue underslab MEP
- Begin slab pours
Central Middle School
Crews have worked on the following:
- Footings and foundation walls
- North parking lot subgrade and curbs
- Undeground plumbing and electrical
- Load bearring CMU walls (Area D, south CY and locker room)
- CMU starter course – Area D, A, and B
- Metal panel an unit masonry mockup
- Install storm lines
Upcoming Construction work:
- North parking lot asphalt base
- Prep and pour slab on grade (Area D and North CY)
- Structual steel – South CY
Sumner HS Addition
Crews have worked on the following:
- SOG at main building, CMU at link building
- Preparation for steel erection
Upcoming construction work
- Installation of level 2 steel beams, decking and stairs
- Fireproofing at Link building