October 23, 2026
District-wide Bond Project Updates - Week of October 19, 2026

Here’s the latest on the ongoing construction projects taking place at KCKPS:
Central Middle School: New Structure
Crews have worked on the following:
- Footings & Foundation Walls
- Underground Plumbing & Electrical
- Storm Lines
- CMU Starter Course
Upcoming Construction Activities:
- Prep & Pour Slab on Grade
- Precast Mockup
- North Parking Lot Site Electrical
Sumner Academy of Arts & Science: New Addition
Crews have worked on the following:
- Geofoam and backfill inside precast
- Roof blocking in preparation for roofing activities
Upcoming Construction Activities
- Underground plumbing and electrical, Slab on Grade
- Continued construction at building connection (Foundation, interior CMU, SOD)
Woodland Hills Elementary School: New Structure
Crews have worked on the following:
- Installation of structural masonry for elevator shaft and structural walls
- MEP in-wall and in-ground installation Area A.
- Construction of roadways, parking lot, laydown yard, temp. Seeding, and installation of erosion control.